Premier Construction Group, Inc. has a wealth of experience in a variety of markets. Following is a sample of a few of our recent projects. Please contact us for additional examples relevant to your specific project.
Gold’s Gym Pleasant Valley
Raleigh, NC
 
Tenant improvements to convert an existing 35,500 s.f. movie theater into a modern fitness center

In four short months, through the holiday season, this project was completed allowing a highly anticipated January opening for the eagerly awaiting members with their New Years resolution of getting fit. This gym features the typical vibrant Gold’s interior finishes including; multicolored rubber flooring, a multitude of bright-colored walls, classy tile locker rooms, custom cabinetry with granite counters, wall mirrors throughout, and a wide range of unique gym flooring. A last minute design of a mezzanine addition created the challenge of erecting structural steel inside the building in conjunction with completing finishes elsewhere, avoiding schedule impact. With a pre-cast plank floor system and parking garage under the entire space, layout of floor penetrations proved an arduous task, along with the difficulty of access to the building. Not only did Premier Construction Group, Inc. overcome the challenges presented, but delivered the building expeditiously while offering the owner cost saving value-engineering solutions.
|
Arby’s Restaurant
Finksburg, MD


Convert Masci Steakhouse to Arby’s Restaurant – 3,650 square feet

A deadline of December 31 gave Premier only 45 days for a complete interior and exterior renovation, which included a new roof and an electrical service upgrade. To add more of a challenge to the task, Premier was asked to run this project simultaneously with the Arby’s Eldersburg project. This was a task that the Premier team was more than able to handle.
|
Taco Bell/Long John Silver's
Hamburg, PA
 
New 2,763 sq. ft. Restaurant

This project consists of the new construction of a combination of two fast food restaurants sharing the same facility with two distinct interior and exterior decor. The project was completed in 77 calendar days even though it was constructed during the winter season. The site development was the challenge on this project with excessive ground water and a landscape wall that had to be redesigned to meet the site conditions. The facility was wood frame construction, ceramic tile floors, FRP wall panels, acoustical ceilings, drywall, exposed structure ceilings in the dining area, and multiple colors through out the store. This design gives the customer a soft and appealing atmosphere for a casual dinning experience.
|
Dunkin Donuts/Baskin Robbins
Harrisburg, PA
 
New 2,760 sq. ft. Restaurant

New construction of a 2,760 square foot restaurant. Construction was of wood framing and roof trusses, rubber roofing, multi-colored EIFS exterior wall finishes, ceramic tile flooring, various wall coverings and plastic laminate panels, wood interior doors, aluminum windows and entrances. High-tec lighting accents the dining area with the multi-colored paints and wall coverings. This facility will soon be the favorite destination for many local residents taking pleasure in their favorite donuts and ice cream.
|
|
 |
|
|